*Recently updated or added projects are highlighted in yellow in the above table*
Jefferson Park Avenue Bridge Replacement Project: Please visit VDOT's website for details on this project and to sign up for e-mail alerts.
Dates: On Going
The Alderman Road Residence Halls require extensive underground utility work. This section of the work, which impacts McCormick Road, was delayed in order to minimize impact to McCormick Road. The UVA winter break is an opportune moment to make necessary utility connections and realignments.
There will be a single lane closure on McCormick Road near the intersection of Edgemont Road from Friday, December 16 through Friday, December 23. Flagmen will direct traffic around the construction. All lanes will be open by 6:00pm every day. Pedestrians will be directed to the west side of the road.
Dates: On Going
The U.Va Children's Hospital (Battle Building) project is underway. Impacts to parking and/or transportation service will be posted on this page as needed.
Dates: December 19, 2011 - December 23, 2011
From December 19th through December 23rd parking at the Culbreth will be closed at all times due to garage maintenance. The Culbreth Garage will need to be vacated by 1:00am December 19th to avoid relocation or tow. Alternative parking can be located at the Emmet Ivy Garage during those times. The map ( located here) shows the affected area as well as a map of alternative parking locations. Parking and Transportation appreciates your cooperation and apologizes for the inconvenience. If you have any questions you may contact our events office at ptevents@virginia.edu.
Dates: April 8, 2011 - April 2012
Due to construction associated with the Drama Building, the A18 lot will be closed for the duration of the project. A18 permit holders will be reassigned to the Culbreth Road Garage (A9). Please contact Caroline Dailey, Reserved Parking Coordinator, at cad@virginia.edu or 434-924-4539 for more information.
Dates: On Going
The Medical Education Building Project is underway. Impacts to parking and/or transportation service will be posted on this page as needed.
Dates: On Going
The Newcomb Hall Renovation project is underway. Impacts to parking and/or transportation service will be posted on this page as needed.
Dates: On Going
The Pavilion IX Construction Project is underway. Impacts to parking and/or transportation service will be posted on this page as needed.
Dates: August 3 - 9, 2011
The Track & Field project is underway. Impacts to parking and/or transportation service will be posted on this page as needed.
Dates: December 20, 2011 - January 25, 2012
Please be advised that the Theatre Project will conduct the second half of the underground Duct Bank installation in a portion of Carrs Hill Road, and in the Campbell Hall service road beginning on December 20, 2011. This work will not affect the main entrance and access to the Carrs Hill residence. The work will be staged in parts and will take 6 weeks to complete.
Part I: December 20 - December 29, 2011
The first part of the work will begin on December 20th and will consist of excavation and the installation of an underground Duct Bank in the intersection of Carrs Hill Road and the Campbell Hall service road. This section of work in the intersection only will take about 9 days to complete and during the course of this work vehicular traffic access will be maintained to rear parking area of the Carrs Hill residence. As before a small vehicle access ramp will be constructed on the east side of the excavation to allow vehicles to safely pass that work area. This work will be complete and unobstructed vehicle access to the rear of the residence will be restored by December 29, 2011.
Part II: December 29 - January 4, 2012
Part two of the work will be the excavation and installation of the Duct Bank from the above intersection to the north side of the Campbell Hall loading dock. This part of the work will begin on December 29th, and will be complete by January 4th, 2012.
Part III: January 5 - January 25, 2012
The final part of the work will be the excavation and installation of the remaining part of the Duct Bank from the loading dock to a point past the parking lot for the DKE House. This work will begin on January 5, 2012 and will be complete by January 25, 2012.
During all work periods construction signs and flagmen will assist traffic and pedestrians to safely pass the work area.
At all times any emergency vehicles will be given priority attention.
Outside work is weather dependant and if this work has to be rescheduled due to inclement weather notice will be provided as soon as possible.
T4 and E3 Permit Holders:
With the construction along Whitehead Road wrapping up, the boundaries of the E3 and T4 parking lots will be changing (see map). Given the new boundaries, if you are interested in exchanging your permit, please contact P&T. Please give us a call at 924-7231 or visit our web site at www.virginia.edu/parking if you have any questions.
Download the T4 and E3 Boundary Map (.pdf)
October 17 - 21, 2011
Partial Lane Closures - Intersection of Whitehead Road and Stadium Road
Please be advised there is work planned on the east elevation of Rice Hall which will require single lane
traffic at the intersection of Whitehead Road and Stadium Road. The work is scheduled to occur during
normal business hours between October 17 - 21. Single-lane traffic will be controlled via flagmen while
the work is in progress. Two-way traffic will resume after the completion of the work shift.
Please be advised this work is weather dependent, and is subject to change as a result of inclement
weather conditions. Future Construction Alerts will keep you updated with the progress of the work
and/or required changes in schedule.